Background

A client was building a 5000 MT controlled atmosphere store in North India and their technical advisor had left the project midway in the month of May. They were stranded and feared losing of revenue for one complete year, they approached us in the last week of July

Key Challenges

Our Solution

We were put up against a very tough task of ensuring that they do not miss the harvesting season and the stored product gives the desired quality. We started with breaking down the entire commissioning schedule into essential and non-essential items.